The Alameda Square Project is moving forward at a slower pace than we had hoped, however we are still here and hope to let out several bid packages in February. Start dates at this time for packages #2-5 are tentative due to some ongoing negotiations. These packages include:
Pkg #1 the asbestos abatement of phase II-prebid meeting 02-09-2009;
notification to plan rooms .....Feb 02
prebid .................................................09
site examinations.......................10-11 Buildings will be open from 8am to 4pm
questions...........................................12 directed to rwolf@kkes.com
answers.............................................13 will be sent to everyone on the prebid sign up sheet
bids due by 4pm in Denver...........17 2200 W Alameda unit 12
fax to Lynn or scan........................18 from Denver office to Boise office
interview.....................................18-19 top bidders
let bid.................................................20
Pkg #2 the excavation and export of the southeast corner of the site including the demolition of the existing carwash and trees, brush, trash, fencing, existing lower retaining wall, and debris as defined in the bid document-prebid meeting 02-12-2009; Pkg #3 650+ feet of retaining wall including the excavation and backfill for the retaining wall-prebid meeting 02-12-2009;
notification to plan rooms........Feb 06
prebid ...................................................12
site examinations...............................---
questions.............................................17 directed to Jcloninger@brightoncorp.com
answers...............................................19 will be sent to everyone on the prebid sign up sheet
bids due by 4pm in Denver.............24 2200 W Alameda unit 12
fax to Lynn or scan...........................25 from Denver office to Boise office
interview........................................26-27 top bidders
let bid...........................................Mar 02
Pkg #4 the demolition and crushing of the Social Services Building-prebid meeting 02-20-2009 and the demolition of phase II buildings-prebid meeting 02-20-2009; Pkg #5 the excavation and preparation of the Lowe’s building pad forthcoming.
notification to plan rooms .....Feb 12
prebid .................................................20
site examinations.......................23-24 Buildings will be open from 8am to 4pm
questions...........................................25 directed to Jcloninger@brightoncorp.com
answers..............................................27 will be sent to everyone on the prebid sign up sheet
bids due by 4pm in Denver....Mar 03 2200 W Alameda unit 12
fax to Lynn or scan..........................04 from Denver office to Boise office
interview.......................................05-06 top bidders
let bid...................................................07
I am sending this information to you to pass on to your members. All meetings will be held at Alameda Square, 2200 W Alameda Ave. at the Social Services Building at the far southern end of the site. All prebid meetings will be held at 1:00 pm on the date named. Anyone interested can email me with the name of their company and what package/s they are interested in bidding to get on the contact list. Plan rooms: Construction News Service, Reed Construction Data, Builders Exchange, CDOT-Construction Development Center, ISQFT, and Denver Public Library...see Denver Area Plan Rooms.
John Cloninger
Project Superintendent Brighton Corporation * 3278 S Wadsworth Blvd, Unit 1 Box 74, Lakewood, CO 80227
Office/Fax 303-937-9685 * Cell 208-283-0550 jcloninger@brightoncorp.com